Which of the following is a requirement for installation permits processed through the boiler section?

  1. They must be filed electronically

  2. They must be posted on the site prior to work

  3. They must be signed by the building inspector

  4. They can be processed after work begins

The correct answer is: They must be posted on the site prior to work

For installation permits managed through the boiler section, it is essential that they are posted on the job site prior to the commencement of work. This requirement serves several important purposes. First, posting the permit ensures compliance and transparency with local regulations and authorities. It allows inspectors and any third parties, such as neighboring property owners or concerned citizens, to be aware of the work being performed and ensures that proper oversight can occur. Additionally, having the permit visibly posted protects the contractor and the property owner by demonstrating that they have obtained the necessary permissions before commencing work, which may help in avoiding potential fines or legal issues down the line. While some permits may need to be filed electronically and signed by authorities, and starting work prior to obtaining a permit can often be a violation of regulations, it is the posting of the permit onsite that provides clear evidence of compliance and serves as a critical step in the installation process.