Should pipe fabricated in the shop be inspected by a quality control manager?

  1. Yes, always before leaving the shop

  2. No, only if there are issues

  3. Only once it is on the job site

  4. No, not required

The correct answer is: Yes, always before leaving the shop

Inspection of shop-fabricated pipe by a quality control manager is a critical process. It ensures that the pipes meet the required specifications and standards before they are shipped out for installation. This step is vital for several reasons. First, conducting inspections prior to leaving the shop allows for the identification of any defects or issues that could compromise the integrity of the piping system once installed. Catching problems early in the fabrication process is more efficient and cost-effective than addressing them on-site or after installation. Second, such inspections ensure compliance with safety standards and regulations, which are essential in preventing failures that could lead to dangerous situations or costly repairs. By verifying that the fabrication has been performed according to established guidelines, the quality control manager plays a key role in maintaining the overall quality and reliability of the piping system. Therefore, the practice of inspecting shop-fabricated pipes before they leave the shop is not just a good quality control measure; it is a necessary step to uphold safety and performance standards across projects.